Vinci A8373Hospital Infill Expansion |
Tweet |
The designers have determined that a formerly integral building wing addition, now nearly “landlocked” amid other hospital additions, be brought down. This will require it be cut, but it isn’t exactly like cutting a birthday cake. This 4d demolition sequence was used to speak to how the cut might be safely made, given only what was conveyed by the RFP. Obviously such an operation will require engineering, but the simplified concept can be demonstrated during a bid interview.