Vinci A9460University Medical Center Headquarters |
Constraints on this end of the worksite include subsurface utilities, a retaining wall and electrical substation, and an access road that can’t be shut down even for a day. The excavation lays back on this side, implying most of the retaining wall will be demolished site utilities relocated.
Take a look at the other end of the site, the mass excavation in total, the worksite overview, or go behind the scenes to see what went into modeling the substation and implications for a skyway to the garage beyond the substation.
This page last modified Monday 23 November 2015.